Pattaya, Thailand— Pattaya city authorities, led by Deputy Mayor Manot Nongyai, performed a website see to keep track of the development of the roadway surface area enhancement task at the crossway of Wat Boonkanjanaram Roadway on Sukhumvit Roadway in South Pattaya. The task intends to boost all 4 crossways along Sukhumvit Roadway, consisting of North Pattaya Junction, Freeway Junction, Wat Boonkanjanaram Junction, and Chaiyapruek Junction.
The very first crossway to go through enhancement, Wat Boonkanjanaram Junction, has actually been closed for about 6 weeks. The task includes resurfacing the roadways with concrete to produce a smoother and more secure surface area. The crossway is anticipated to resume with signal lights by August 15. The total task, started in April, is set to be concluded by February 2024.